GSoC: Pharo UML

Manager: Reinout Stevens
Start: May 24, 2010
Finish: August 16, 2010
Report Date: April 9, 2010

Gantt Chart

WBS Name Work
     
1 Research 10d
2 Main library 14d
3 Integrating Pharo 12d
4 Converting Classes to UML 12d
5 Midterm Evaluation
6 Main library 2nd phase 7d
7 Integrating Pharo 2nd phase 6d
8 Converting Classes to UML 2nd phase 6d
9 Website 13d
10 Improve documentation 5d
11 Final Evaluation
Week 21, 2010 Week 22, 2010 Week 23, 2010 Week 24, 2010 Week 25, 2010 Week 26, 2010 Week 27, 2010 Week 28, 2010 Week 29, 2010 Week 30, 2010 Week 31, 2010 Week 32, 2010 Week 33, 2010
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Research May 24 Jun 4 10d 0%
2 Main library Jun 4 Jun 23 14d 0%
3 Integrating Pharo Jun 24 Jul 9 12d 0%
4 Converting Classes to UML Jun 24 Jul 9 12d 0%
5 Midterm Evaluation Jul 12 Jul 12
6 Main library 2nd phase Jul 12 Jul 20 7d 0%
7 Integrating Pharo 2nd phase Jul 21 Jul 28 6d 0%
8 Converting Classes to UML 2nd phase Jul 21 Jul 28 6d 0%
9 Website Jul 29 Aug 16 13d 0%
10 Improve documentation Aug 9 Aug 13 5d 0%
11 Final Evaluation Aug 16 Aug 16

Resources

Name Short name Type Group Email Cost